This appendix describes installation procedures you should use for installing LightStream 1010 ATM switches after your first installation.
The installation and configuration of the LightStream 1010 ATM switch can be separated into specific steps. If each step described in the Quick Installation Worksheet (see Table C-1) is completed following the instructions provided in this publication, LightStream 1010 ATM switch installation should be successful. If the installation fails to make the LightStream 1010 ATM switch function properly in the first attempt, the Quick Installation Worksheet can be used to systematically check that each step was performed correctly.
Copy the Quick Installation Worksheet and initial each procedure as it is completed. Each task in the Quick Installation Worksheet should be verified by the person performing the installation and dated for the permanent site record.
Every task in the Quick Installation Worksheet is described in detail in this publication or in the LightStream 1010 ATM Software Configuration Guide, and is listed in the index.
Table C-1 : Quick Installation Worksheet
| Task | Completed |
|---|---|
| Complete Switch Installation Checklist | |
| Complete Switch Component Checklist | |
| Complete Port Configuration Worksheets | |
| Rack-mount the switch | |
| Connect cables | |
| Connect power cables | |
| Switch power on | |
| Configure line [aux|console] | |
| Configure SNMP | |
| Set clock (optional) | |
| Test the configuration | |
|
|
Copyright 1988-1996 © Cisco Systems Inc.